Decabling Project Overview Mandate, organisation, general planning, coordination, safety LS2 COMMITTEE – 3 rd meeting, 27 May 2016 G. Cumer, EN/ACE/OSS.

Slides:



Advertisements
Présentations similaires
Définition des termes spécifiques
Advertisements

SECURITE ELECTRIQUE.
HCC meeting – jeudi 14 Mai Résultats des tests HC-AUG ( ) EN-EL, HCC Team et Hugues Thiesen.
ST Operation Committee Résumé du 5-2 au 2-4 Suivi Opération Affaires en cours Affaires résolues Travaux Divers Piquets ST.
Vision Globale Domaine d’application Objectif
Meeting 2015#1 Linac4 Coordination of Installation January 2015 – schedule follow-up EDMS J. Coupard EN-MEF1 week 3.
1 avril 2003ST Workshop 2003 Thoiry1 L’ AOC informatisé: C.Jacot, E.Sanchez-Corral, L. Symons un moyen de prévention et de management Avec la complicité.
Tests AUG aux points 5&4 (10&12 déc.) Objectifs Utiliser les tests annuels des AUG afin d’évaluer l’impact d’une coupure électrique sur les différents.
PH SPace Overview Board Space POlicy Board A.Petrilli, June 19, 2014.
MANDAT INTERNATIONAL DES TABLES RONDES POUR LES AIRES PROTEGEES Décision X/31(11-12): Encourage bailleurs et Parties en voix de développement de soumettre.
J-B. Lallement, B. Mikulec
BENCHMARK JOBS Marie-Laure Rivier – January 2015.
TBM implantation in CLEX 1 TaskDurationDate 1Remove the safety barriers0.5 days1.06 2Preparation of the storage tables inside CLEX0.5 days1.06 3Radioprotection.
EPRUS Etablissement de Préparation et de Réponse aux Urgences Sanitaires.
Experiments, Schedule & Access to the hall. Magdalena Kowalska.
Depuis Describing how long one has been doing something.
ÉCOLE POLYTECHNIQUE CONCOURS 2010 Workshop NSERC scholarship application 23 avril 2015 École Polytechnique.
What is this role and why are we all concerned? Palluel Julien - BE/CO meeting, Dec 2011.
EU Joint Programming: Belgium Expert meeting on EU Joint Programming April 26th 2013.
Modèles d’interaction et scénarios
Welcome everyone.
Proposals/Propositions Organisation of Union Events together with National Events Members will recall that in recent years, the level of participation.
Slide 1 of Slide 2 of 35.
Session : Modele plan d’action Template Action Plan
10 – ACTIVITES DES ENTREPRISES
African Centre for Statistics United Nations Economic Commission for Africa Session : Etapes de mise en oeuvre du SCN 2008 Milestones for implementation.
Slide 1 of Slide 2 of 37.
EN LS1 CV/ACCESS/Cabling Work co-activities February 5th, 2013 R. Brown/S. Mataguez EN/MEJ/INJ LS1 CV/ACCESS/Cabling Work co-activities EDMS
BAF3 Civil engineering Status -6 June 2013 EDMS approval procedure for « Plans d’execution » launched on 16/05/2013. Drawings released on 28/05/2013 (some.
Welcome To Waterside Village Community Channel Stay tuned for important information about your community.
General description General description of the tasks to be accomplished Each Muon Station is composed of two parts: one on the Cryo side (US), the other.
Remaining LHCb related tasks during LS1 with DT involvement LHCb/DT meeting, May 19, 2014.
Orientation 2006 by Pierrette Guimond Asssistant Director Graduate Programs School of Nursing.
EDHEC OPEN INNOVATION 2016 #OpenInno 2016 [Bus. Case title – Company] Company LOGO.
LS1 : ACTIVITES LHC. Jean-Frédéric FUCHS | SU pendant LS1 day | | INDICO | page 2 LHC : Activités prévues pendant le LS1 Nivellement.
YETS 2015/2016 Travaux EN/EL [ hors CF ] G. Cumer 22 septembre 2015.
S. EVRARD, Latest news from TCC2/TDC2. Outline 2 - Sébastien EVRARD  2013 schedule  New vacuum leak under investigation  Cable and cable tray re-routing.
S. Grau & AS Team 9/15/2015 EDMS XETS coordination meeting 2.
LINAC3 INSTRUMENTATION STATUS S. Sadovich – 29 Apr 2015 S.Sadovich on behalf of F.Roncarolo 29 Apr
Meeting of Experiments Dismantling Coordination E. Cennini.
1 1. Linac4 – 2012 Progress New 2.8MW klystron H- source DTL CCDTL RFQ.
Dashboard 2 October 2015 PH SO1. PREVENTION INCIDENT MANAGEMENT COMMUNICATION.
Setting Europe in motion : Favoriser l’intégration Un projet de développement scolaire soutenu par L’Union Européenne Action Comenius 1.3 – 3 eme année.
D. Chapuis - D. Raffourt GS/ASE 07/10/2015 EDMS – SPS YETS coordination meeting 1.
TT2 Infrastructure upgrade 22 sptembre2015 Christophe Mutin.
Procédure identification/déconnexion Pour le groupe de travail dédié.
Fabien Plassard December 4 th European Organization for Nuclear Research ILC BDS MEETING 04/12/2014 ILC BDS MEETING Optics Design and Beam Dynamics Modeling.
CCP Report CSR 15 February CSR meeting Mandate CSR Advisory body to the SCC Oversees all matters regarding restaurants/cafeterias/vending machines.
Localisation des cables dans le booster. Objectifs Extraire depuis les DEC un fichier qui reprend toutes les données qui permettent de renseigner différentes.
Verification des DEC Comparaison des nombre de câbles dans les DEC et valeurs du Dashboard Vérification dans les DEC de l’existence de doublons Vérification.
BOOSTER ORPHAN CABLES Georgi Minchev Georgiev EN-EL Emmanuel SAID BE-CO 20/11/2015 General De-cabling Project Meeting #5.
Barry Callebaut Processus de Governance LSS
Procédure identification/déconnexion Pour le groupe de travail dédié.
French leve 1 - Homework due on May 2, 2016 – vocabulary  You are given at the beginning of the year the global list of the vocabulary list of BON VOYAGE,
Point de situation BE-CO sur l'identification des câbles les tests Emmanuel SAID Herve Cornet.
DISMANTLING OF WATER COOLED CABLES IN BA5 OF SPS Georgi Minchev Georgiev EN-EL-CF 08/10/2015.
LIU and EL activities De-cabling strategy from EYETS to LS2 in PSB, SPS and PS Meeting 18 May 2016 Injector De-cabling Project G. CUMER, EN-ACE-OSS.
Tests annuels des AUG du LHC A.Burdairon _ G.Cumer.
Traffic Sign Recognition Jacob Carlson Sean St. Onge Advisor: Dr. Thomas L. Stewart.
SPS préparation travaux LS2
Decabling Project Overview Mandate, organisation, general planning, coordination, safety PSB/PS/TT2 EYETS 2016–2017 coordination meeting, 2nd June 2016.
De-cabling strategy during YETS August 2017
Injectors de-cabling Project General information June 2017 INDICO:
Activités LHC pour BE/ICS Systèmes d’Alarmes YETS et LS2
Decabling Project Overview Mandate, organisation, general planning, coordination, safety PSB/PS/TT2 EYETS 2016–2017 coordination meeting, 22 sept 2016.
Activités EN/EL-FC EYETS16-17
Injectors de-cabling Project EYETS 2017_ Consignations SPS pour le projet de-câblage 23 novembre 2016 G. Cumer, EN/ACE/OSS.
« Chargés de consignation » & projet de-câblage
CRG TM for YETS November 6th 2017.
Safety Talk EN DSO & EROS
Transcription de la présentation:

Decabling Project Overview Mandate, organisation, general planning, coordination, safety LS2 COMMITTEE – 3 rd meeting, 27 May 2016 G. Cumer, EN/ACE/OSS

Decabling Project Overview Scope of the project Organization Master schedule Dashboard after the YETS Nature des travaux (sécurité électrique) Contraintes Booster EYETS Co-activités et contraintes LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Project scope * The De-cabling project scope is to identify and remove obsolete cables within the PS Booster, SPS and PS, until the end of LS2. The activities will be organized according to the following priorities and goals: First priority PSBOOSTER; Second priority SPS; Third priority PS. *IEFC LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Prioritization* The identification of the obsolete cables in the PS Booster is the top priority, because of the needs for new cables for the LIU project, with the following deadlines: Labelling and disconnection during YETS ; Removal of obsolete cables during EYETS and if necessary YETS For SPS5 and SPS3: Identify respectively 50% and 40% of existing cables for removal, because of the congestion of the cable trays and the need to pull new cables. Moreover, the project team will have to closely follow the needs of the LIU project taking into account the availability of resources. For the PS, the project team will identify the obsolete cables. The deadline is: during 2016, the project team will propose possible identification and removal slots, taking into account the availability of resources and further needs of LIU project. *IEFC LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Master schedule LS2 COMMITTEE – 3 rd meeting, 27 May 2016 If necessary

Decabling Project Overview Organization of the project A Core team project including members of EN/EL - EN/ACE and HSE/RP Project link persons from 14 groups for identification and disconnection phases : BE/BI – BE/CO – BE/RF – BE/ICS – TE/ABT – TE/EPC – TE/MSC – TE/VSC – TE/MPE – HSE/RP – IT/CS – EN/CV – EN/EL – EN/STI EN/EL is the main budget owner (for removal phases). The identification phases are funded by the groups concerned. EN/ACE has a slight budget for the cables without owner. LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Organization of the project, documentation Project Management Plan – being circulating for comments: EDMS EDMS Project documentation : EDMS CERN EDMS CERN Indico : Dedicated share point : LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Dashboard after the YETS LS2 COMMITTEE – 3 rd meeting, 27 May 2016 Bravo à S. Evrard et tous les intervenants!  G. Cumer new project leader since February 2016

Decabling Project Overview Nature des travaux (sécurité électrique) En application de la norme UTE , le core team du projet de decâblage des Injecteurs a conduit une analyse de risque sur la nature des travaux et des interventions pour ce projet. En application des recommandations du DSO/EN, du Safety Support Officer du LS2 et des Operational Safety Support Officers, les travaux et les interventions effectués dans le cadre de ce projet ont été classifiés en tant que Travaux de nature électrique. LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Nature des travaux (sécurité électrique) En conséquence, les travaux et les interventions liés au projet devront être réalisées par du personnel électricien dûment habilité : Les travaux liés à l’identification et la déconnexion des câbles obsolètes devront être réalisés par des chargés d’intervention des groupes concernés, avec une habilitation BR ; Les travaux de dépose et enlèvement des câbles obsolètes devront être réalisés par des opérateurs électriciens (contractant EN/EL) avec une habilitation H1/B1, sous la responsabilité d’un chargé de travaux (contractant EN/EL) habilité H2/B2 ; Le chargé de travaux devra avoir reçu et signé des attestations de consignation pour travaux de la part des Chargés de Consignation des groupes concernés (ayant des équipements installés). LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Classification des travaux Les travaux et les interventions effectués dans le cadre de ce projet ont été classifiés en tant que Travaux de nature électrique. LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Booster EYETS 2016 : contraintes et coactivités Systèmes devant rester sous tension, opérationnels pour la sécurité des personnes  Eclairage de sécurité  Désenfumage  Contrôle d’accès  Détection incendie  AUG  Ventilation (tbc HSE/RP)  Alarmes de niveau 3  Alarmes évacuation  RAMSES LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Booster EYETS 2016 : contraintes et coactivités Systèmes devant rester sous tension, opérationnels pour les travaux du EYETS  Buffer zone  Ascenseur  Pont roulant  Eclairage Normal  Star-point  Bâtiment 37  Coffrets de prises dans la machine LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview Booster EYETS 2016 : contraintes et coactivités Structures et faux-planchers LS2 COMMITTEE – 3 rd meeting, 27 May 2016 Identify areas which require reinforcement by mapping, securing and strengthening of critical supports which are in close proximity to the racks 5 days at the start of EYETS dedicated to corrective interventions on the “Faux Planchers” Follow the procedures and practices set out by C. Bedel during the YETS cable identification campaign. [VIC 2384: VIC cable identification campaign PSBEX-YEA1 YETS ] En étude avec HSE

Decabling Project Overview Booster EYETS 2016 : contraintes et coactivités Synergie avec des travaux EYETS, co-activités ( D. Hay ) LS2 COMMITTEE – 3 rd meeting, 27 May 2016  BCER: Low Voltage distribution systems  Consolidation réseau basse tension EN/EL (nouveaux tableaux Machine et alimentations des racks par le haut, dépose des gaines canalis dans les faux planchers) Il y a une synergie à faire cette consolidation en même temps que la dépose des câbles ! (mêmes contraintes de sécurité, mêmes consignations et faux planchers)  Tirages de câbles pour LIU  Travaux EYETS Ces travaux sont possibles en coactivités avec EN/EL (présentation prévue fin Juin)

Conclusions Changement de chef de projet depuis Février 2016 Poursuite de la mise en application de la stratégie définie en 2015, avec ses priorités chronologiques 1. PSB - 2.SPS - 3.PS (centre anneau) &TT2 En 2016, les objectifs du projet sont: Préparer et réaliser les campagnes de de-câblage du PSB et du SPS5L, prévues pendant l’EYETS : travail de nature électrique (méthodes et procédures), contraintes générés par le projet et par les autres co-activités. Realiser l’identification des câbles obsolètes dans le PS (centre anneau et TT2) Le projet de de-câblage du PS Booster se situe clairement sur le chemin critique du EYETS pour PS Booster  le planning est en cours d’optimisation/discussion Les activités de de-câblage dans le SPS5L ne semblent pas critiques en terme de réalisation et de planning, les faux planchers ont été consolidés pendant le YETS , les chemins de câbles sont différentiés. LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Backup slides G. Cumer, EN/ACE/OSS

Decabling Project Overview Procédure de consignation phase de déposes des cables LS2 COMMITTEE – 3 rd meeting, 27 May 2016 Y Z W Attestations de consignations pour travaux (d’ordre electrique) Chargé de travaux “X” (H2/B2) Exécutants électriciens (H1/B1) Chargé de travaux “Y” (H2/B2) DSO departement B Pilote du groupe resp. des travaux DSO departement A Identification, via les DSO, des groupes devant consigner leurs équipements, DRAFT Chargé de consignation HC/BC X

Decabling Project Overview _ PS BOOSTER LS2 COMMITTEE – 3 rd meeting, 27 May 2016

Decabling Project Overview PS centre anneau b LS2 COMMITTEE – 3 rd meeting, 27 May 2016

EYETS Marzia Bernardini & Julie Coupard – LSC 1st April 2016 For the LHC the duration of the EYETS is 19 wks For the SPS, PS and the PSB, the duration is aligned to the LHC. This is due to the requests concerning: -the decabling project and its implementation strategy; -the anticipation of LIU activities during the EYETS These durations includes the tests and HWC periods HWC, Machine check out and Beam commissioning Working time