North area S. Girod, EATM, 22-03-2016
Calage des aimants zone nord Calages en cours: TCC2: 7 aimants TT81 - TT82 - EHN1: 11 aimants TT83: 2 aimants De nombreux elements faisceaux a deplacer, remettre en place, aligner, reconnecter…. Details: https://edms.cern.ch/document/1584695/ S. Girod, 22/03/2016 2
TCC2 - All XTAX are out of chains for maintenance and tests 2 collimators replaced: XCSH 022.068 & XCSV 041.047 (Abou) BBS 1245 & vacuum chamber removed (upstream T6) Water leaks on magnets are being repaired S. Girod, 22/03/2016 3 3
TCC2 Work notification with new matrix request to be done Replacement of XTAX in interlock chains: H2-H4 : TAX 021023 TAX 1001 TAX 021025 TAX 1002 (not used) TAX 022023 TAX 1003 (not used) TAX 022025 TAX 1004 H6-H8 : TAX 042018 TAX 1005 TAX 042020 TAX 1006 (not used) P0: TAX 043018 P4 TAX 1007 TAX043020 P4 TAX1008 TAX 062052 P6 TAX 1009 TAX062054 P6 TAX 1010 M2: TAX 061052 TAX 1011 (not used) TAX 061054 TAX 1012 Work notification with new matrix request to be done S. Girod, 22/03/2016 4 4
H4 Setup pour NA63 zone PPE134: 2 MBPL gap 140mm + vacuum Ø273 S. Girod, 22/03/2016 5 5
H6 XFFV.041.451 et XDWC 488 à réinstaller et aligner Chambre à vide à déposer zone 146 en aval de XCET505 pour utilisateur S. Girod, 22/03/2016 6 6
détails: https://edms.cern.ch/document/1572394/ H8 Dépose faisceau H8 VLE terminé Installation / reconfiguration du faisceau zone PPE148 en cours détails: https://edms.cern.ch/document/1572394/ S. Girod, 22/03/2016 7 7
K12 Target T10 repaired T10 upstream shielding installed Survey on beam line to be done. S. Girod, 22/03/2016 8 8
K12 He Exhaust piping works next 2 weeks Double air wall to be closed big fisc installation / alignment S. Girod, 22/03/2016 9 9