Outline 2 - Sébastien EVRARD 2013 schedule New vacuum leak under investigation Cable and cable tray re-routing
Schedule 3 - Sébastien EVRARD Activities DurationGroupNov'13Dec' TCSC removal 1wEN-HE,STI TT20 QNL magnet exchange 1wEN-HE Splitter removal 3wEN-HE MDLV removal 1wEN-HE Contingency 1w Goal end 2013: 6 hot items out of the way.
Optimization step 2- Removal of hot items 4 - Sébastien EVRARD Removal of hot items from the worksites: TCSC removed first and brought to B.955 3 splitter2 magnets and 2 MDLV removed and stored in TDC2
New vacuum leak 5 - Sébastien EVRARD
Visual inspection 6 - Sébastien EVRARD TCSC connexion Splitter magnet 2
7 - Sébastien EVRARD Remove and re-route 5 cable trays above Splitter2 magnets Re-route PVC insulated cables feeding the magnets upstream MDLV_ and replace them by PVC-free ones Cable and cable tray re-routing MSSB 3 MSSBTCSC Integration by C. Magnier, EN-MEF MDLV_ Control 1 Control 2 DC1 DC2 GS Current proposal Beam direction
Modèle 3D Catia ST _ 01 NOUVEAU ROUTING PROPOSE Chemins de Cables fixés au mur coté Jura Accès libre pour Lignes CV + Vannes
NOUVEAU ROUTING PROPOSE 2016mm 1798mm 1566mm 2230mm 2458mm Services généraux Puissance 2 Puissance 1 Contrôle Echelle existante (MSSB)