HIGH RADIATION TO MATERIALS WG3 – E XPERIMENTAL A REA HiRadMat project Team Meeting 14/04/2011 Activities TS week 13 Production for test area On-going design studies Activities TS week 19&25 Ans Pardons– EN/MEF
2
HiRadMat 2 Installed week 13, total dose ~1mSv TS week 13: Construction Dump 4m downstream of T9 Ans Pardons EN/MEF Dump 4m Support TED Dump 4m T9
3
HiRadMat 3 TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±) Total dose preparation: ~0.9mSv, installation: ~0.2mSv TS week 13: Installation TED Ans Pardons EN/MEF
4
HiRadMat 4 TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±) TS week 13: Installation TED Ans Pardons EN/MEF Interference between crane lifting beam and new (downstream) roofblock Solution: use intermediate hooks (made for test tables) Intermediate hook Short hook (for comparison) No interference
5
HiRadMat 5 Priority: base tables: Reception aluminium support structure: week 15 assembly week 16 Reception tables plates: week 17 add to support structure & paint week 17 Reception additional small pieces (wedges,...): week 18 final assembly of entire table week 18 &start of week 19 for installation week 19 Intermediate crane hooks (also for closing T9 shielding) Reception hooks: week 16 closing roof can in short access (assuming we can use monte-charge) Structure for passage of cables to test stand Study on-going, orders week 16, reception probably for week 19 Production for Test area & Muon Dump Ans Pardons EN/MEF
6
HiRadMat 6 Passage cables in TNC Material – slope – remote installation & dismounting Design studies Ans Pardons EN/MEF
7
HiRadMat 7 Remote dismounting base tables Chariot for test tables Design studies Ans Pardons EN/MEF
8
HiRadMat 8 (liste non-exhaustive, en ordre chronologique) Installation ventilation autour de T9 (2 jours, PP) Ouverture toit, installation TED, fermeture toit T9 (1 à 2 jours, YS, DG) prêt pour installation BPKG Installation tables de base et alignement (2 jours, ML, DDP, KB) (plus test de manutention si temps disponible, autrement pendant prochain arrêt) prêt pour installation BLMs Pose peigne et pose câbles dexpérience (à confirmer, GG) Installation supports en zone de décroissance (ML, DDP) (plus test de manutention si temps disponible, autrement prochain arrêt) Installation supports plaques marbres et blocs acier (si temps disponible, autrement pendant prochain arrêt) Nettoyage, peinture Activities week 19 (pardon my French) Ans Pardons EN/MEF