La présentation est en train de télécharger. S'il vous plaît, attendez

La présentation est en train de télécharger. S'il vous plaît, attendez

Civil engineering for LIU – PS

Présentations similaires


Présentation au sujet: "Civil engineering for LIU – PS"— Transcription de la présentation:

1 Civil engineering for LIU – PS
Shielding of route Goward

2 Status – 22 may 2012 Document « Civil engineering for increasing the radiation shielding on the route Goward. Passage over the PS » completed → EDMS approval procedure ongoing (25 may 2012) CE execution drawings completed → EDMS approval procedure ongoing (22 may 2012) Tender documents completed → EDMS approval procedure completed (16 may 2012) Market survey completed → list of firms to be finalized ( translation in english of the tender documents to be confirmed depending on the nationality of the selected firms) NEXT STEPS Launch call of tender Organize an information campaign to the attention of the occupants of the center of the ring NEW ! Two “sondages” requested by RP to determine if the ground around the PS is contaminated → potential impacts on the method of execution and the cost / delay of work Reminder: the assumption for this project was that there was no RP constraints for materials and/or workers

3 Installation de chantier

4 Démolition et démontage

5 Terrassement et accès provisoire

6 Pieux

7 Dalle

8 Mur bâtiment 365

9 Mur de soutènement du parking

10 Mur de soutènement sud-est

11 Situation finale

12 Profil en long de la route

13 Marquage et signalisation

14 Provisional Schedule Travaux préparatoires avant chantier de génie civil: -Evacuation des transformateurs –EN/EL -Abattage des arbres GS/IS -Dépose des candélabres – GS/SE -Dépose des moniteurs RP - DGS/RP - Autres??


Télécharger ppt "Civil engineering for LIU – PS"

Présentations similaires


Annonces Google