nTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN preparatory works (antennas removal, radio club barrack removal, asbestos removal B559, deviation of the optical fibre, power and water temporary supply for the worksite) finished on 30/04/2013 Contractors main works started on 13/05/2013: Done: – Worksite installation – Demolition of barrack 559 – Deviation of the existing networks – Earthworks – Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery – Piles Ongoing: – Concreting of the building foundations on the ISR slab L.A.Lopez
Désamiantage Dépose baraque du Radio-club
Démolition B559
Terrassement Cérémonie 1 er coup de pelle
Puits du faisceau Carottage faisceau dans galerie nTOF
Puits fini du faisceau Déviation des réseaux
Réalisation des pieux
Planning objectif
Next steps Concreting works September 2013 Finishing works (waterproofing, insulation, doors, « chape », painting) October- November 2013 Landscaping November 2013 L.A.Lopez