1
SPS LS1 Planning meeting (No.26) 11/12/13
David Mcfarlane
2
Topics Lifts and Monte-charges. Upcoming works. Maintenance 18 kV.
CSA presentation Planning. False floors open in the Bas. E.C.Rs. Christmas Vacation Access rights and safety equipment. Important Information. A.O.B
3
Lift Maintenance Dec/Jan
4
Upcoming works Replacement of Irradiated cables (BA1)
Now until March 2014 Civil Engineering works (TT10) Now until End of year Replacement of Septas (BA2) 28th Oct until end of year Kicker conditioning (BA6) Dec to mid Jan Re-installation of beam line and equipment in TT10 January 2014
5
Maintenance 18 kV EMD2. 9 JURA du vendredi 20 dec au samedi 21 dec
La maintenance 18 kV de la station majeure de JURA ME9 est impérative et critique La maintenance des barres des tranches 1 et 3 en cours actuellement . Elle n’affecte pas le fonctionnement de l’auto transfert et du réseau secours. Au contraire de la maintenance des barres de la tranche 2 qui nécessitera la mise hors service du système auto transfert et de la liaison Normal/secours. L’absence de la fonction secours ME9 a pour conséquence l’interdiction d’accès en souterrain LHC1 –ATLAS –LHC18 – SPS6 –SPS7 pendant les 3 à 4 jours de maintenances Par ailleurs des interventions du contractant Schneider E078 sont déjà planifiées W50 et W51 au LHC6 et LHC7… Suite à nos divers échanges de ce jour et au TIOC, nous pouvons proposer le planning suivant Lundi 16 déc. au mercredi 18 déc. : maintenance 18kv LHC7 selon planning LHC Jeudi 19 déc. : jour de repos des techniciens Schneider (et OP) Vendredi 20 déc. au dimanche 22 déc. : maintenance des barres de la tranche 2 JURA : -> pas d’accès en souterrain LHC1 –ATLAS –LHC18 – SPS6 –SPS7 A noter qu’il n’y aura pas de coupure utilisateur, les réseaux aval étant réalimentés sans coupure ACCESS INTO BA6 &BA7 WILL BE BLOCKED FROM THURSDAY LUNCHTIME (19TH DECEMBER)
6
CSA presentation
7
NOTRE MISSION Interface avec les responsables des accès des zones (GS-ASE) S’assurer que les accès aux accélérateurs sont fermés, Faciliter l’accès des usagers/intervenants, S’assurer que les intervenants respectent les réglements Droits d’accès, Port des EPI, Bonne utilisation PAD/MAD intervenir sur les alarmes Faire remonter les anomalies liées aux accès Vers TI (problème technique) Vers GS-DI (non-conformité des personnels / non respect des procédures)
8
NOTRE BESOIN Échanciers des interventions par zone
Appeler l’agent «ZORA» (n° ) En début et fin d’intervention Quand une porte est «forcée» dans les accélérateurs Refermer toutes les portes que vous ouvrez Autres problèmes lié aux accès
9
SPS LS1 schedule Beam on EPC Commissioning tests
Beam off : 16/02/13 Beam on: 13/10/14 Open Access : 27/03/13 Close Access : 27/06/14 Beam on Cool down/RP survey and Magnet tests Cool down NO ACCESS Fibres 18 KV Kicker Survey Civil Engineering in TT10 RF upgrade works Survey RF upgrade works EPC works Cables Survey Survey Kicker Cables Survey EPC works Survey Survey Maintenance General Maintenance General Magnets Magnets Magnets Magnets Kicker Magnets Magnets Cables Magnets 18 KV Magnets General maintenance General maintenance Crab Cavities General Maintenance Cooling tower 863 General Maintenance Survey Vacuum Ring-main Ring-main Ring-main Vacuum Ring-main Septa works Ring-main Vacuum Ring-main Fibres Septa works Ring-main Prep work in LSS1 18 KV General Maintenance Maintenance General Vacuum Vacuum RF Upgrade works Cables Survey Horizontal Vertical smoothing Cool down Limited ACCESS Fibres TT20 pipework 18 KV CV maintenance CV maintenance UA works Civil Engineering Irradiated Cables 18 KV Fibres CV maintenance Fibres Cables Cables Cables 18 KV Cables EL Studies Civil Engineering TT10 Consolidation Cables replacement Septa Civil Engineering Civil Engineering CV studies RF Upgrade works Crab Cavities Civil Engineering Civil Engineering RF Upgrade works Re-install equipment removed for cable works RAL Magnets CV works Fibres Cables Magnets Magnets Magnets Magnets Magnets Magnets Magnets EPC Commissioning tests Vacuum Cold check out & Start-up DSO tests/HV tests Protons to the North Area Protons to LHC Ions to NA61 CV Controls upgrade Re-route Cabling
10
False floors lifted in Surface BAs
Below is a table showing the dates that EL will be pulling cables at each point of the SPS. During these periods large sections of the false floor in these surface buildings will be lifted. Any works in the BA’s that involve lifting of the false floors MUST be reported to the Coordination team BAs Cabling pulling start Cable pulling end BA1 (TS1- works) BA1 (Irradiated cable works) BA1 (Fibre Optics) 29/04/2013 08/10/2013 08/04/2013 02/08/2013 14/02/2014 24/04/2013 BA2 06/01/2014 11/03/2014 BA3 BA3 (Fibre Optics) 27/03/2013 22/04/2014 31/05/2013 06/05/2014 BA4 BA4 (Fibre Optics) 27/05/2013 07/10/2013 12/07/2013 25/10/2013 BA5 BA5 (Fibre Optics) 30/09/2013 24/05/3013 11/10/2013 BA6 BA6 (Fibre Optics) 13/09/2013 13/5/2013 08/11/2013 24/05/2013 BA7 14/10/2013 07/11/2013 If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first.
11
Engineering Change Requests
Templates and Guidelines for Engineering Change Requests: EDMS: SPS ECR template (in DFS):
12
Current ECR’s for LS1 Removal of AEWB Pick-up from position to 31502 (EDMS No ) RELEASED Removal of a BPWA Pick-up from position to 31101 (EDMS No ) RELEASED Installation of a new Wideband Kickers system in position 32173 (EDMS No ) RELEASED Installation of a new HBW Damper Pick-up in place of BPWA & AEWB 31932 (EDMS No ) RELEASED Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2 (EDMS No ) RELEASED Reinstallation of pump and gauges (Pirani + Penning) in (vacuum sector 150) (EDMS No ) RELEASED Modification LSS1 sectorization (new VVSF + displacement VVSB 11772) (EDMS No v.2) RELEASED Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS. (EDMS No ) UNDER IMPLEMENTATION
13
Current ECR’s for LS1 Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5. (EDMS No ) RELEASED SPS Beam Position Monitoring Prototyping Setup in LSS4. (EDMS No ) RELEASED Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper. (EDMS No ) RELEASED Installation d'un nouveau moniteur de position de type BPCR en LSS2 au (EDMS No ) RELEASED Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel. (EDMS No ) UNDER IMPLEMENTATION Interlocking of Injection Tunnel upstream areas with LHC powering. (EDMS No ) RELEASED Move of BPH to BPH (EDMS No ) RELEASED Optical Fibre Racks. (EDMS No ) UNDER IMPLEMENTATION
14
Current ECR’s for LS1 Removal of old fixed TMP vacuum groups in (EDMS No ) RELEASED BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS). (EDMS No ) UNDER IMPLEMENTATION Installation de Coffrets d'Alimentation en LSS1 et TT10. (EDMS No ) RELEASED Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement. (EDMS No ) UNDER IMPLEMENTATION Installation de nouveaux chemins de câbles en LSS1+ du SPS. (EDMS No v.2) RELEASED TPSN replacement in LSS2 of SPS. (EDMS No v.1) RELEASED Installation d'un nouveau chemin de câbles en LSS2- du SPS. (EDMS No v. 0.1) IN WORK Replacement of pumps in 3 tanks MKP in LSS1 of the SPS . (EDMS No v. 0.1) UNDER APPROVAL
15
Current ECR’s for LS1 Suppression of VVFA in LSS1 of SPS. (EDMS No v. 0.1) UNDER APPROVAL New shielding wall behind TIDV in SPS . (EDMS No v. 0.1) IN WORK
16
The Christmas Vacation
There is no planned works or accesses into the SPS during the 2 week vacation. There are no requests for services during this period?? BA6 and BA7 will be closed from 12:00 on Thursday the 19th December
17
Access rights and safety equipment
Everyone who enters the SPS MUST have the following: Completed the correct courses. Safety course levels 1,2 and 3. Habilitation Electrique. Radiological Protection. Self Rescue Mask Training. The correct access authorisation (via EDH). A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. Helmet plus Light. Please note that personnel are not allowed to work in the tunnel alone!!
18
Important information
Useful Contact Numbers SPS Coordination Team David MCFARLANE Franck BAIS – James RIDEWOOD Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Elodie Aubert Kurt Weiss (BA1) Coordination Safety Emmanuel Paulat – John Etheridge
19
A.O.B. Please make sure you fill out you IMPACTS correctly!!!!
There are currently 19 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT. If you have ANY concerns about not being complete before the 27th June I need to know about it NOW!!!! The SPS cooling towers will be stopped 03/02/14 to 07/02/14 for EL works on switchboard, transformer and SPS pumping station LS2!!!!!! Work has already begun on the planning for LS2. If you are planning on doing any major works in LS2 for consolidation then we need to know about it now. Please can you send me an stating the main tasks you are planning/hoping to do during LS2
20
SPS coordination website
\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1 Next meeting 08/01/2014 112-R-028