YETS preparation S. Girod, EN-MEF EATM
North Area H2 & H4 alignment (Survey) H8: démontage blanche VLE, redistribution des quadrupoles PR 534 in EHN1 (EN-HE) TDC2 AHU control upgrade (EN-CV) BA82 chilled water pipes (EN-CV) Collimator consolidation to be continued (EN-MEF): LIGNEELEMENTPOSITIONETATCOMMENTAIRE MAINTENANCE TCC2 H4XCSH Ruban instable sur les guidesPrevoir remplacement shuntdown 2015 TT81 H4 XCSV Ruban abiméMettre capuchon, Prevoir maintenance shutdown 2015 TT82 H6 XCSV Point dur dans la mécaniqueRemise à neuf de la mecanique shuntdown 2015 EHN1 H2 H2 XCSH Ruban abiméPrevoir remplacement ruban shuntdown 2015 EHN1 H8 H8 XCSH Ruban instable sur les guidesPrevoir remplacement guide&ruban shuntdown 2015 TCC8&ECN3 TT84-M2
East Area 5 MTV’s BTV’s (BE-BI)
AD BHN34 magnet refurbishment Vacuum ion pumps replacement BCCCA maintenance/upgrade ELENA magnet DC cable pulling campaign Installation of the AD extraction line towards ELENA (open shielding in sector 1, line 7000) Pursue ELENA hardware installation G-Bar shielding installation (if funded) and LINAC installation
nTOF Filter box installation in horizontal beam line
HiRadMat Not yet defined
AWAKE